Completed Tasks in Gantt chart
Hello, in the Gantt view, when I change a status to completed, what dictates if it is shown as a red "overdue". Is there a "completed" date that i'm missing, or is it governed by the day I change the card from In Progress to Completed?
Ideally i'd like to be able to put in a custom completed date and see how much overdue the task took compared to the projected time, i.e. the "Due Date".
Hello,
now the Gantt chart works as you described, the due card is shown as red, when you complete it it becomes green, meaning it's completed.
The Gantt chart doesn't provide a comparison you described. Please describe us your needs and we will consider applying this new functionality.
Best regards,
Katarzyna Bobrowska